PROJECT PLANNING TASK
Launch a client onboarding portal in 8 weeks. Team: 1 project manager (20 h/week), 2 developers (30 h/week each), 1 designer (15 h/week for the first 4 weeks, then 5 h/week). The payment-provider integration needs a vendor approval that takes 10 working days and cannot start until the legal team signs the contract (expected end of week 1). Developers estimate the build at 330 hours. The designer estimates design work at 60 hours.
TASK: Produce an actionable project plan: weekly milestones, owners, dependencies, a critical-path summary, top 5 risks with mitigations, and a clear statement of whether the 8-week deadline is feasible with the stated capacity. Show your capacity arithmetic.